787 delivery date set for mid-first quarter 2011

Boeing says it now expects delivery of the first 787 in the middle of the first quarter 2011.

The delivery date revision follows an assessment of the availability of an engine needed for the final phases of flight test this fall.

While Boeing works closely with Rolls-Royce to expedite engine availability, flight testing across the test fleet continues as planned.

Boeing said last month that the cumulative impact of a series of issues, including supplier workmanship issues related to the horizontal stabiliser and instrumentation delays could push first delivery of the 787 a few weeks into 2011. The delay in engine availability has extended that estimate to mid-first quarter 2011.

www.boeing.com  